Deputy PM asks for prompt preparations for Long Thanh airport project

Deputy Prime Minister Trinh Dinh Dung has asked for the feasibility report on the Long Thanh International Airport project to be completed and submitted soon so that it can be considered by the National Assembly in late 2019, ensuring that the construction of the project starts in 2020 as scheduled.

An overview of the meeting 
The Deputy PM addressed a meeting in Hanoi on February 12 on the results of the feasibility study for the first phase project, which was jointly carried out by the Airports Corporation of Vietnam and a joint venture comprising of firms from Japan, France and Vietnam (JFV) from June 2018.

On June 2, 2018, the JFV signed a contract with Heerim Architects and Planners on the designing of the airport’s terminals.

According to the consultation agency, detailed designs of the project will largely be completed by April 2019. Connectivity methods and investment plans were also proposed.

Deputy PM Dung recognised the efforts of the Ministry of Transport and relevant agencies, as well as the People’s Committee of Dong Nai in ground clearance and the project’s implementation.

He stressed the need to build the airport to the highest standards so as to ease the overloading of Tan Son Nhat International Airport in Ho Chi Minh City, turning Long Thanh into an international and regional aviation transit centre.

He asked for the careful calculation of transport demands and the division of exploitation among airports in the country and region, thus optimising the efficiency of the project.

The airport should apply modern technology and ensure safety, convenience, quality, efficiency, defence, security, and environmental protection criteria, he said.

The Deputy PM also suggested the mobilisation of capital for the project from private businesses, minimising the use of State budget.

The Long Thanh International Airport has a total area of more than 5,580 ha, spreading across six communes in Long Thanh District, the southern province of Dong Nai. It is set to have a total investment of 336.63 trillion VND (14.8 billion USD), with construction divided into three phases.

In the first phase, a runway and a passenger terminal, along with other supporting works, will be built to serve some 25 million passengers and 1.2 million tonnes of cargo each year. This phase is hoped to be finished by 2025.

In the second phase, an additional runway and passenger terminal will be constructed to serve 50 million passengers and 1.5 million tonnes of cargo per year.

After the third phase, the airport will be able serve 100 million passengers and 5 million tonnes of cargo annually.
Mời quý độc giả theo dõi VOV.VN trên

Related

Long Thanh International Airport capital debate divides NA
Long Thanh International Airport capital debate divides NA

The missing capital for site clearance at Long Thanh International Airport has yet to be determined as members of the NA are still debating whether they should allocate part of the capital reserves of the 2016-2020 medium-term public investment fund or part of the VND80-trillion fund serving key projects. 

Long Thanh International Airport capital debate divides NA

Long Thanh International Airport capital debate divides NA

The missing capital for site clearance at Long Thanh International Airport has yet to be determined as members of the NA are still debating whether they should allocate part of the capital reserves of the 2016-2020 medium-term public investment fund or part of the VND80-trillion fund serving key projects. 

ACV picks coconut leaf design for Long Thanh International Airport
ACV picks coconut leaf design for Long Thanh International Airport

Of the three passenger terminal design plans submitted to the Prime Minister, Airport Corporation of Viet Nam (ACV) showed its preference for Plan LT-07, the architectural plan for Long Thanh International Airport inspired by the coconut leaf image.

ACV picks coconut leaf design for Long Thanh International Airport

ACV picks coconut leaf design for Long Thanh International Airport

Of the three passenger terminal design plans submitted to the Prime Minister, Airport Corporation of Viet Nam (ACV) showed its preference for Plan LT-07, the architectural plan for Long Thanh International Airport inspired by the coconut leaf image.

Long Thanh international airport to create growth momentum
Long Thanh international airport to create growth momentum

VOV.VN - The Vietnamese government is hurrying to finish the ambitious Long Thanh international airport by 2025. Once operational, Long Thanh is expected to become one of the most state-of-the-art airports in Southeast Asia. 

Long Thanh international airport to create growth momentum

Long Thanh international airport to create growth momentum

VOV.VN - The Vietnamese government is hurrying to finish the ambitious Long Thanh international airport by 2025. Once operational, Long Thanh is expected to become one of the most state-of-the-art airports in Southeast Asia.