Power plant construction begins after 5-year delay

Construction of the Hai Duong-Vietnam thermo power plant officially kicked off on March 27 in Hai Duong province’s Phuc Thanh commune after a five-year delay.

The power plant will have two 600MW-steam turbines run by JAKS Hai Duong Power Company Ltd under the Malaysia-based JAKS Resources Berhad Group and the China Power Engineering Consulting Group. It has a total capital investment of US$1.86 billion.

According to an agreement signed in July last year, the Hai Duong power plant, built under the Build-Operate-Transfer (BOT) model, will be handed to the Vietnamese government after 25 years of operation.
The first turbine is expected to start running in December 2019 while the second turbine is slated for June the following year.

The thermo power plant, covering an area of more than 300ha spread over Phuc Thanh, Quang Trung and Le Ninh communes in Kinh Mon District, was approved by the Vietnamese Government in August 2011.

Yet the failure of joint venture co-operative agreements between the investor, JAKS, and Malaysian companies Island Circle Investment Holding Ltd and Sanjung Merpati Sdn Bhd, as well as China-based energy firms Wuhan Kaidi Electric Power Engineering Co and Meiya Power Ltd, left the project up in the air for nearly five years.

The power plant marked the first project by JAKS group in Vietnam’s power generation industry.
Mời quý độc giả theo dõi VOV.VN trên

Related

PM attends Vung Ang 1 thermo-power plant inaugural ceremony
PM attends Vung Ang 1 thermo-power plant inaugural ceremony

Prime Minister Nguyen Tan Dung attended a ceremony to inaugurate the Vung Ang 1 Thermal Power Plant in Ky Anh district, the central province of Ha Tinh on September 17. 

PM attends Vung Ang 1 thermo-power plant inaugural ceremony

PM attends Vung Ang 1 thermo-power plant inaugural ceremony

Prime Minister Nguyen Tan Dung attended a ceremony to inaugurate the Vung Ang 1 Thermal Power Plant in Ky Anh district, the central province of Ha Tinh on September 17. 

Binh Thuan thermo power plant expansion kicks off
Binh Thuan thermo power plant expansion kicks off

(VOV) -Construction of a US$2 billion expansion of the Vinh Tan Thermal Power Plant got underway on July 18 in Binh Thuan province.

Binh Thuan thermo power plant expansion kicks off

Binh Thuan thermo power plant expansion kicks off

(VOV) -Construction of a US$2 billion expansion of the Vinh Tan Thermal Power Plant got underway on July 18 in Binh Thuan province.

PVN signs US$1.2 billion deal for thermo-power unit
PVN signs US$1.2 billion deal for thermo-power unit

The national oil and gas group PetroVietnam on July 7 signed two sub-contracts under an engineering, procurement and construction (EPC) contract worth US$1.2 billion to build the Quang Trach 1 thermo-power plant with two of its subsidiaries. 

PVN signs US$1.2 billion deal for thermo-power unit

PVN signs US$1.2 billion deal for thermo-power unit

The national oil and gas group PetroVietnam on July 7 signed two sub-contracts under an engineering, procurement and construction (EPC) contract worth US$1.2 billion to build the Quang Trach 1 thermo-power plant with two of its subsidiaries.