Hanoi elevated train pilot run delayed

The planned pilot run of the first elevated train in Hanoi next month will be delayed amid lagging construction progress and financial difficulties.

The railway connecting Cat Linh and Ha Dong was initially scheduled to have its pilot run in early October before it officially opens to the public in the second quarter of next year. But Transport Deputy Minister Nguyen Ngoc Dong admitted after a survey trip to the project last week that it was "almost impossible" to meet the deadline as several sections of the railway project were still under construction.

The railway’s subcontractors said that the main contractor - China Railway 6th Bureau Group - was late in paying them and responsible for letting the construction falling behind schedule.

Dong said that the project was facing financial problems too, as more than US$250 million in loans from China to build the railway were yet to be disbursed due to legal issues.


"The Ministry of Transport is cooperating with relevant parties to conclude the matter and to obtain the capital for the project as soon as possible," he said.

He also said that the main contractor in the meantime must keep pace with the schedule it previously committed to.

The transport ministry would soon ask the Chinese Embassy in Vietnam to work with the China Railway 6th Bureau Group on the issue, Dong said.
Mời quý độc giả theo dõi VOV.VN trên

Related

No serious injuries after train hits soft drink delivery truck
No serious injuries after train hits soft drink delivery truck

VOV.VN - A Vietnam Railways passenger train is running again after a collision with a truck carrying water and other soft drinks in Hanoi on the morning of Wednesday, September 13.

No serious injuries after train hits soft drink delivery truck

No serious injuries after train hits soft drink delivery truck

VOV.VN - A Vietnam Railways passenger train is running again after a collision with a truck carrying water and other soft drinks in Hanoi on the morning of Wednesday, September 13.

Train carrying 214 passengers derails in northern Vietnam
Train carrying 214 passengers derails in northern Vietnam

VOV.VN - A Vietnam Railway train carrying 214 passengers derailed today (September 8)while entering the Bim Son Railway Station in northern Thanh Hoa Province, reported Vietnamnet.

Train carrying 214 passengers derails in northern Vietnam

Train carrying 214 passengers derails in northern Vietnam

VOV.VN - A Vietnam Railway train carrying 214 passengers derailed today (September 8)while entering the Bim Son Railway Station in northern Thanh Hoa Province, reported Vietnamnet.

International container train starts trial run
International container train starts trial run

 The Hanoi Railway Transport Joint Stock Company (Haraco) has successfully conducted a trial run of an international container train connecting China’s Guangzhou province and Hanoi’s Yen Vien town.

International container train starts trial run

International container train starts trial run

 The Hanoi Railway Transport Joint Stock Company (Haraco) has successfully conducted a trial run of an international container train connecting China’s Guangzhou province and Hanoi’s Yen Vien town.